File #: AM No. 23-146   
Type: Consent Item Status: Passed
File created: 9/27/2023 In control: City Council
On agenda: 10/17/2023 Final action: 10/17/2023
Title: Approve Interlocal Agreement with City of Kirkland for the Signal and Intersection Improvements Project at 132nd Avenue NE and NE 100th Street
Attachments: 1. Agenda Memo, 2. Attachment A: Interlocal Agreement, 3. Attachment B: Conceptual Project Plan, 4. Attachment C: Preliminary Cost Estimate, 5. Attachment D: Project Information Sheet
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Jon Spangler
City Engineer


TITLE:
title
Approve Interlocal Agreement with City of Kirkland for the Signal and Intersection Improvements Project at 132nd Avenue NE and NE 100th Street


OVERVIEW STATEMENT:
recommendation
NE 132nd Avenue is on the border of the City of Redmond and the City of Kirkland. Both cities agree that traffic patterns warrant a signalized intersection at NE 100th Street. The cities propose to share the cost of the project equally. The total project cost is estimated at $2,218,035, with Redmond's share being $1,109,018. Kirkland will manage the project and coordinate with Redmond. Project completion is targeted for 2025.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Transportation Master Plan
* Required:
Interlocal agreements require City Council approval
* Council Request:
N/A
* Other Key Facts:
Funding for Redmond's share is mostly from Microsoft mitigation funds.


OUTCOMES:
Approval of the agreement will provide the funding for the design and construction of the signalized intersection allowing for more efficient traffic flow in the area and improved bicycle and pedestrian safety.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
Kirkland plans to lead outreach efforts to both Redmond and Kirkland residents.
* Outreach Methods and Results:
Project notifications on both city websites, direct contact with area residents as project progresses, message boards before and during construction.
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
$1,109,018 (Redmond's share of the $2,218,035)

Approved in current biennial budget: ? Yes ? No ? N/A

Budget Offer Number:
CIP

Budget Prio...

Click here for full text