Title: Approval of Final Contract with Lakeside Industries Inc., in an Amount of $995,650, and Acceptance of Construction for the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Additional Project Information
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Mike Haley
Project Manager
Public Works
Steven Gibbs
Capital Projects Division Manager
Public Works
Brandon Buehler
Acting Deputy Director


TITLE:
title
Approval of Final Contract with Lakeside Industries Inc., in an Amount of $995,650, and Acceptance of Construction for the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) Project


OVERVIEW STATEMENT:
recommendation
Public Works is requesting Council to approve the final contract and accept construction for the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) Project, (project No. 2311). This contract with Lakeside Industries Inc. had a base bid amount of $1,217,250, plus or minus change orders and bid items increases or decreases, resulting in a final contract amount of $995,650.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Transportation Master Plan
Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the City to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.
* Required:
Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
Public Works is requesting this item go forward for Council approval at the March 17, 2026, Council business meeting.


OUTCOMES:
West Lake Sammamish Parkway is a key corridor for Redmond. The project rehabilitated the asphalt roadway of West Lake Sammamish Parkway between Marymoor Way and Leary Way NE. The project met the objectives.


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or...