Title: Approval of the Final Contract with Dickson Company, in the Amount of $333,304, and Acceptance of Construction for the Old Fire House Teen Center Demolition Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works Chris Stenger 425-403-5510
DEPARTMENT STAFF:
Parks Danika Globokar
Deputy Parks Director Parks Casey Huebner
Facilities Manager Public Works Steve Gibbs Capital Construction Division Manager Public Works John Mork Project Manager

TITLE:
title
Approval of the Final Contract with Dickson Company, in the Amount of $333,304, and Acceptance of Construction for the Old Fire House Teen Center Demolition Project


OVERVIEW STATEMENT:
recommendation
Public Works is requesting Council approve the final contract and accept construction for the Old Fire House Teen Center Demolition project (No. 2569).

The project completed hazardous material abatement and demolition of the existing Old Fire House building, preparing the site for construction of the new Teen Center. The contract with Dickson Company had a base bid amount of $388,895, plus or minus change orders and bid item increases or decreases, resulting in a final contract amount of $333,304.

Council acceptance is the final step in completing the construction contract. Following acceptance, the project will proceed through the remaining contract close-out requirements, including release of retainage in accordance with RCW 60.28 after receipt of required clearances from the Washington State Departments of Revenue and Labor and Industries and completion of the mandatory 45-day waiting period for filing claims and liens.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

Relevant Plans/Policies:
Facilities Plan
Required:
City Council approval is required to accept a Public Works contract exceeding $300,000 pursuant to 2018 City Resolution 1503.
Council Request:
N/A
Other Key Facts:
The project has completed hazardous material abatement and demolition activities necessary to prepare ...