TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Planning and Community Development
Carol Helland
425-556-2107
DEPARTMENT STAFF:
Planning and Community Development
Micah Ross
Senior Engineer
Planning and Community Development
Michael Hintze
Planning Manager
Planning and Community Development
Seraphie Allen
Deputy director
TITLE:
title
Acceptance of Grant Funding for 156th Ave Shared Use Path Project
OVERVIEW STATEMENT:
recommendation
The City has been awarded $770,715 for the design phase of the 156th Ave Shared Use Path project from the Puget Sound Regional Council. The project extents are from 4300 Block to NE 51st Street. Council is asked to accept the grant funding and authorize the Mayor to sign the Local Agency Agreement (LAA) with WSDOT for Disbursement of Federal Grant Funds.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
Transportation Master Plan
* Required:
RCW 35A.11.040 requires Council approval to accept grant funds
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The grant funding will be used for the design phase of the project to construct this key non-motorized connection to the Redmond Technology Station.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
Total Project Cost: $5,436,500
Total Design Phase Cost: $891,000
Grant Funding for Design: $770,715
Approved in current biennial budget: ? Yes ? No ? N/A
Budget Offer Number:
000039
Budget Priority:
Vibrant and Connected
Other budget impacts or additional costs: ? Yes ? No ? N/A
If yes, explain:
N/A
Funding source(s):
Transportation CIP, Federal Grant
Budget/Funding Constraints:
Federal funds must be obligated by June 1, 2024; th...
Click here for full text