Title: Award Progressive Design-Build (PDB) Contract to Lease Crutcher Lewis WA, LLC of Seattle, Washington, for the Teen Center Project
Attachments: 1. Agenda Memo, 2. Attachment A: Teen Center Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: Progressive Design-Build Contract
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Committee of the Whole - Public Safety and Human Services
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Parks Loreen Hamilton 425-556-2336 Public Works Chris Stenger
425-403-5510

DEPARTMENT STAFF:
Public Works Shailee Jain Project Manager Public Works Eric Dawson Engineering Supervisor Public Works Steve Gibbs Capital Division Manager Parks Danika Globokar Deputy Parks Director


TITLE:
title
Award Progressive Design-Build (PDB) Contract to Lease Crutcher Lewis WA, LLC of Seattle, Washington, for the Teen Center Project

recommendation
OVERVIEW STATEMENT:
Parks and Public Works are requesting to award the PDB Contract for the Teen Center Project, Project No. 2571, to Lease Crutcher Lewis WA, LLC in the amount of $1,486,030 for the completion of the Validation Phase Work.

The PDB Contract requires the Design-Builder to perform all design and construction services. The Work will be completed in three phases: the Phase 1a Validation Phase, Phase 1b (Preconstruction and Design), and Phase 2 (Construction).

Approval is currently being requested for the entire PDB Contract, with funding limited to the Validation Phase scope of Work. Future funding requests for Phases 1b and 2 will be submitted to the Council as Contract Amendments before any further work is started.

The City conducted a competitive Progressive Design-Build selection process in accordance with RCW 39.10, resulting in the selection of Lease Crutcher Lewis WA, LLC as the highest-scoring team. The team demonstrated relevant project experience, a strong approach to teen-centered community engagement, and an understanding of the Teen Center’s project goals and priorities.

For reference: PDB lets the City hire one accountable team of architects and builders early (Design-Builder team), chosen for their qualifications, and then shape the project's scope, schedule and price together with that team before committing to a final construction price. A primer regarding the PDB process...

Click here for full text