Approval of the Consultant Agreement Supplement 2 with David Evans and Associates, Inc. in the Amount of $225,000 for NE 40th Street Shared Use Path (156th Avenue NE to 163rd Avenue NE)
OVERVIEW STATEMENT:
recommendation
The Consultant Services Agreement Supplement 2 with David Evans and Associates, Inc. (DEA) is for Construction Engineering and Management Services for the project. It increases the maximum amount payable to $876,000.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503).
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The NE 40th Street Shared Use Path, located on the south side of NE 40th Street from 156th Ave NE to 163rd Ave NE, will provide a half-mile comfortable bicycle and pedestrian connection to the Redmond Technology light rail station in the Overlake Regional Growth Center and support future extensions east to the Idylwood Neighborhood.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
Consultant Supplemental Agreement $225,000
Approved in current biennial budget: ? Yes ? No ? N/A
Budget Offer Number:
CIP
Budget Priority:
Vibrant and Connected
Other budget impacts or additional costs: ? Yes ? No ? N/A
If yes, explain:
N/A
Funding source...