TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Planning and Community Development
Carol Helland
425-556-2107
DEPARTMENT STAFF:
Planning and Community Development
Seraphie Allen
Deputy Director
Planning and Community Development
Michael Hintze
Transportation Planning Manager
Planning and Community Development
Micah Ross
Senior Engineer
TITLE:
title
Approval of a Consultant Agreement with Toole Design for Engineering Services for the 148th Ave Safety Corridor Project in an Amount Not to Exceed $300,000
OVERVIEW STATEMENT:
recommendation
Toole Design has been selected to perform design engineering services for the 148th Ave Safety Corridor Project (NE 31st St to Willows Road). The total contract amount is not to exceed $300,000. Staff are requesting approval for the Mayor to sign the consultant agreement, and approval to secure right-of-way an/or easements needed to construct the project. The project is being funded by Highway Safety Improvement (HSIP) funding and is identified in the City's Safer Streets Action Plan.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
Capital Investment Program (CIP), Transportation Master Plan (TMP)
TMP Pedestrian Plan Strategy 2: Construct prioritized low-stress pedestrian crossings
* Required:
RCW 39.80 and City Purchasing Policies and Procedures require Council authorization for the mayor to sign the contract.
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
Design and construction of this project helps implement the projects and actions identified in the City's Safer Streets Action Plan and will improve safety for residents and employees along the corridor accessing transit and other services.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
Community engagem...