File #: AM No. 25-044   
Type: Consent Item Status: Passed
File created: 3/11/2025 In control: City Council
On agenda: 4/1/2025 Final action: 4/1/2025
Title: Award Bid to Alpha Developers, LLC of Seattle, WA, in the Amount of $929,829 for the Fire Station 17 Siding Replacement Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Vangie Garcia
Deputy Director
Public Works
Steve Gibbs
Capital Projects Division Manager
Parks
Quinn Kuhnhausen
Facilities Manager
Public Works
John Mork
Project Manager


TITLE:
title
Award Bid to Alpha Developers, LLC of Seattle, WA, in the Amount of $929,829 for the Fire Station 17 Siding Replacement Project


OVERVIEW STATEMENT:
recommendation
This contract with Alpha Developers, LLC in the amount of $929,829 is for construction of the Fire Station 17 Siding Replacement Project.

Public Works is also requesting Council increase the total funding for this project from $1,119,620 to $1,299,620.

During routine inspection, Facilities staff discovered moisture intrusion behind the siding of the building which is causing the siding to fail. Facilities staff is recommending replacing the siding to prevent further damage to the building envelope. Work on this project includes replacing the weather barrier and flashing as well as replacing the exterior siding.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
CIP
* Required:
Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
N/A


OUTCOMES:
This project will replace the building weather barrier, flashing and exterior siding. This will prevent further damage to the building structure and extend building life.


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
This work will take place on the fire station property and will not impact neighbors or traffic.

* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
$929,829

Approve...