TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
Public Works Director
DEPARTMENT STAFF:
Public Works
Aaron Noble
Project Manager
TITLE:
title
Approval of the Consultant Services Agreement Supplement 01 with David Evans and Associates, in the Amount of $117,218, for the 156th Cycle Track Project
OVERVIEW STATEMENT:
recommendation
This consultant services agreement supplement with David Evans and Associates for $117,218 is for construction engineering support services for the 156th Cycle Track project, Project No. 20022001. It increases the maximum amount payable to $886,218. The original Consultant Agreement for the design of the 156th Cycle Track was for $769,000. The original agreement did not expect consultant services during construction (SDC) because it was not known at the time what the scope of those services would include. To date 99.7% of the design budget has been spent. This supplement provides funding for project management support during construction such as requests for information, submittal review, change orders, etc. and not inspection or construction management. The project estimated that these services would be 15% of the construction costs or about $500K and the proposed amount contained in this contract is below that spending target. The project will begin incurring costs for these services as soon as the contract is executed, and submittals begin in early July.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The 156th Cycle Track project will build a modally separated bicycle and pedestrian pathway along...
Click here for full text