Title: Teen Center Project Update
Attachments: 1. Agenda Memo, 2. Attachment A: Teen Center Rebuild Project Information
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Committee of the Whole - Parks and Environmental Sustainability
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Parks Loreen Hamilton 425-556-2336 Public Works Chris Stenger (Interim Director) 425-403-5510
DEPARTMENT STAFF:
Public Works Shailee Jain Senior Engineer Public Works Eric Dawson Capital Supervisor
Public Works Steve Gibbs Capital Division Manager Parks Danika Globokar Deputy Parks Director



TITLE:
title
Teen Center Project Update


OVERVIEW STATEMENT:
recommendation
Parks and Public Works are providing an informational monthly update on the Teen Center Project.
body

? Additional Background Provided in Attachment A


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

Relevant Plans/Policies:
Parks, Arts, Recreation, Culture, and Conservation Plan (PARCC)
Teen Services Engagement Report (2025)
Community Priorities for the Future of Redmond’s Community Centers (2017)
Required:
Council Action AM No 25-184
Council Request:
N/A
Other Key Facts:
N/A


OUTCOMES:
We are taking steps towards implementing the Teen Center Project in accordance with Council Action AM No 25-184: “Approval to Rebuild the Teen Center on the Same Location. Prioritize Expedience in Construction, Centering Teen Voices in the Design Process, and Including Music Performance Space and a Dedicated Recording Studio to Continue the Old Firehouse Teen Center Legacy”


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

Timeline (previous or planned):
Community engagement will be a key part of the project moving forward. An engagement plan will be developed as part of the project.?
Outreach Methods and Results:
N/A
Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
N/A

Approved in current biennial budget: ? Yes ? No ? N/A

Budget Offer Number:
545

Budget Priority:
Healthy & Sustainable

Other budget impacts or additional costs: ? Yes ? No ? N/A
If yes, explain:
N/A

Funding source(s):
N/A