Consultant Agreement for Feasibility Study of Fire Station 11
OVERVIEW STATEMENT:
recommendation
The Fire Department is seeking Council authorization to enter into a consultant agreement with TCA Architecture + Planning to conduct a feasibility study for Fire Station 11. The study will evaluate rebuild and renovation options on the station's current site and provide cost estimates to support future budget planning.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
Redmond 2050
Capital Facilities Plan 2050 - General Government Facilities
Redmond Fire Functional Plan - 2025-2050
General
* Required:
N/A
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The study will provide the City with a clear understanding of whether Fire Station 11 should be renovated or rebuilt on its existing site, informed by the building's current condition and operational needs identified through the Facilities Condition Assessment, the Fire Functional Plan, and the Capital Facilities Plan. It will deliver site and facility assessments, feasibility analyses, and budget-level cost estimates that represent the logical next step in planning-supporting informed decision-making and setting the foundation for future capital budgeting.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
$125,000
Approved in current biennial budget: ? Yes ? No ? N/A
Budget Offer Number:
100.60101.00410.52210.9077-100-86
Budget Priority:
Safe and Resilient