Skip to main content
City of Redmond Logo
File #: CM 26-146   
Type: Committee Memo Status: Agenda Ready for Committee of the Whole
File created: 2/24/2026 In control: Committee of the Whole - Planning and Public Works
On agenda: 3/3/2026 Final action:
Title: Progress Update - MOC Campus Redevelopment Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786
Parks
Loreen Hamilton
425-556-2336

DEPARTMENT STAFF:
Public Works
Amy Kim
Capital Project Manager
Public Works
Eric Dawson
Engineering Supervisor
Public Works
Steve Gibbs
Capital Projects Division Manager
Public Works
Brandon Buehler
Acting Deputy Public Works Director


TITLE:
title
Progress Update - MOC Campus Redevelopment Project


OVERVIEW STATEMENT:
recommendation
Public Work is providing an update on the ongoing validation activities for the Maintenance and Operations Center (MOC) - Campus Redevelopment Project, Project No. 2501.

In additional to general project status update - noting that MOC updates are also included as part of the Quarterly CIP reporting - staff will provide a refresher on the Progressive Design Build (PDB) delivery method and how it is being applied to the MOC project.

This refresher is timely as an upcoming contract amendment will be brought forward for approval to authorize transition into the next phase of work, which includes advancing design and potentially initiating select early work packages.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Capital Investment Program
Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the City to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.
Maintenance and Operations Center Master Plan
* Required:
N/A
* Council Request:
N/A
* Other Key Facts:
This effort is part of the regular updates Public Works is providing on the progress for the MOC project.


OUTCOMES:
Engagement of all stakeholders during validation will promote clear communication and effective collab...