TO: Committee of the Whole - Finance, Administration, and Communications
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Technology and Information Services
Michael Marchand
(425) 556-2173

DEPARTMENT STAFF:
Technology and Information Services
Jeremy Mikkola
Business Solutions Manager


TITLE:
title
??Approval of Annual CUES GraniteNET Contract?


OVERVIEW STATEMENT:
recommendation
??Approve the Mayor to sign an updated contract with CUES, in the Amount of $146,788, to support Stormwater and Wastewater pipe inspection program.?
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
N/A
* Required:
??Council approval is required for contracts that exceed $50,000.?
* Council Request:
N/A
* Other Key Facts:
N/A


OUTCOMES:
??This contract provides the City with a modern platform to support wastewater and stormwater pipe inspections, enhancing the existing staff-led inspection practices with an additional layer of review supported by AI-enabled analysis.
?
?Implementation of CUES GraniteNET defect coding and prescriptive planning increases consistency and operational efficiency in inspection review, supports timely identification of asset conditions, and reduces the risk of undetected issues.
?
?These capabilities strengthen proactive asset management, extend the useful life of critical utility assets, and promote reliable service delivery to the community.
?
?GraniteNET positions the City to continue evolving its asset management practices while enabling data informed maintenance planning and long-term asset stewardship. ?


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
??$146,788?

Approved in current biennial budget: ? Yes ? No ? N/A