TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Phil Williams
425-556-2880
Planning and Community Development
Carol Helland
425-556-2107
DEPARTMENT STAFF:
Public Works
Bassam Al-Ali
Construction Project Manager
Public Works
Adnan Shabir
Senior Engineer
Planning and Community Development
Peter Dane
Senior Planner
TITLE:
title
Award Bid to Lakeside Industries in the Amount of $1,817,990, and Approve Consultant Agreement Supplement No. 2 with KPG Psomas, Inc. in the Amount of $50,000, for the 90th St. Pavement Preservation Project
OVERVIEW STATEMENT:
recommendation
Award a construction contract to Lakeside Industries of Issaquah, WA, in the amount of $ 1,817,990 for construction of the 90th St. Pavement Preservation project, Project No. 20012026. Approve Consultant Services Agreement Supplement No. 2 with KPG Psomas, Inc. in the Amount of $50,000 for construction support services for the project. The project is a pavement grind and overlay between Willows Road and Redmond Woodinville Road.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
A complete pavement resurfacing of NE 90th Street between Willows Road and Redmond Woodinville Road that includes new channelization, new vehicle loop detectors, ADA curb ramps with associated APS upgrades to the current standards, and a complete pavement rehabilitation that, with proper maintenance, is expected to last 20 years or longer.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
$2,59...