TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786
DEPARTMENT STAFF:
Public Works
Lisa Rigg
Senior Engineer
Public Works
Deepali Jodh
Senior Project Manager
Public Works
Chris Stenger
Deputy Public Works Director
Public Works
Steve Gibbs
Capital Projects Division Manger
TITLE:
title
Approval of a Consultant Agreement with OTAK, in the Amount of $207,958, for the Connection to King County Wastewater System - Avondale Way
OVERVIEW STATEMENT:
recommendation
Public Works is requesting approval of a consultant agreement with OTAK in the amount of $207,958. This agreement is for design services for the Connection to King County Wastewater System - Avondale Way, which will replace 20 lineal feet of existing 18" reinforced concrete pipe with 27" reinforced concrete pipe. The work will include a new saddle manhole at the connection point with the King County Trunk, and abandonment of the existing connection.
Three consultants were selected from the MRSC roster for Engineering Services to submit proposals. Two proposals were received, and OTAK's proposal was rated the highest. Scope and budget were then developed with OTAK to move forward.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
General Sewer Plan
Community Strategic Plan - Objective #1:
Invest in infrastructure preservation and replacement across the city to maintain the current level of service, the reliability of capital assets and provide timely and cost-effective replacement.
* Required:
Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503).
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The project will increase the undersized section of pipe in the Avondale Wastewater Conv...
Click here for full text