File #: AM No. 22-031   
Type: Consent Item Status: Passed
File created: 1/5/2022 In control: City Council
On agenda: 3/15/2022 Final action: 3/15/2022
Title: Approval of Final Construction Contract in the Amount of $4,070,470, with T-Bailey, Inc. of Anacortes, Washington, and Acceptance of Construction for the SE Redmond Tank Painting and Seismic Upgrade Project No. 20021801
Attachments: 1. Agenda Memo
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Phil Williams
425-556-2880

DEPARTMENT STAFF:
Public Works
Steve Flude
City Engineer - Acting EUSD Manager
Public Works
Jon Spangler
Construction Division Manager
Public Works
Joseph O'Leary
Project Manager


TITLE:
title
Approval of Final Construction Contract in the Amount of $4,070,470, with T-Bailey, Inc. of Anacortes, Washington, and Acceptance of Construction for the SE Redmond Tank Painting and Seismic Upgrade Project No. 20021801


OVERVIEW STATEMENT:
recommendation
The City owns and operates a 4.5-million-gallon water storage tank in SE Redmond. The steel tank was constructed in 1996 and was scheduled for exterior and interior paint recoating. The work included the blast removal of all existing paint surfaces. Additionally, to meet current building code requirements, a seismic upgrade interior structure steel frame system was constructed. The project also included the replacement of new safety railings, support piping and storm gutters.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
N/A
* Required:
N/A
* Council Request:
N/A
* Other Key Facts:
N/A

OUTCOMES:
Completed scheduled city water system maintenance for the SE Redmond Tank with the addition of code required seismic upgrade.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
Construction was scheduled from August 2020 to September 2021.
* Outreach Methods and Results:
Given the close proximity of the Evans Creek Apartments to the SE Tank blasting operations, contractor work schedules were shared with Evans Creek Property Manager.
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:

Current Project Budget

Water CIP
$5,887,698


Estimated Project Costs

Design Phase
$655,482
Construction Phase
$4,5...