TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786
Parks
Loreen Hamilton
425-556-2336
DEPARTMENT STAFF:
Public Works
John Mork
Project Manager
Parks
David Tuchek
Parks and Facilities Operations Manager
Parks
Quinn Kuhnhausen
Facilities Manager
TITLE:
title
Award of Bid to CDK Construction Services, Inc., in the Amount of $720,195, for the Redmond Maintenance Operations Center - Plumbing and ADA Upgrades Project and Increase the Total Funding for this Project from $550,000 to $1,132,632
OVERVIEW STATEMENT:
recommendation
This contract with CDK Construction Services, Inc., is for construction of the Redmond Maintenance Operations Center - Plumbing and ADA Upgrades project, Project No. 20012107.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to award a construction contract over $300,000 per 2018 City Resolution 1503
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
The Redmond Maintenance Operations Center Building 1 was constructed in 1976. After years of daily use by City maintenance staff, the plumbing lines need replacement. This project will replace the existing plumbing lines, improve ADA accessibility, and make other improvements to the men's and women's locker rooms.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
The renovation work will be limited to the men's and women's locker room in building 1 of the Redmond Maintenance Operation Center. City staff will be notified regularly of upcoming construction activities.
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
$720,195
Approved in current biennial budget: ? Yes ? No ? N/A
Budget Offer Number:
CIP
Budget Priority:
Vi...