File #: AM No. 18-132   
Type: Consent Item Status: Passed
File created: 7/16/2018 In control: City Council
On agenda: 9/4/2018 Final action: 9/4/2018
Title: Approval of Final Construction Contract in the Amount of $481,815.60, with Michels Corporation, of Salem, Oregon, and Acceptance of Construction for the Wastewater and Stormwater System Rehabilitation Cured In-Place Pipe (CIPP), Project No. 20021709 and 20021708
Attachments: 1. Agenda Memo No. 18-132, 2. Attachment A: Vicinity Map

MEMO TO:                     Members of the City Council

FROM:                     Mayor John Marchione

SUBJECT:                     


title

Approval of Final Construction Contract in the Amount of $481,815.60, with Michels Corporation, of Salem, Oregon, and Acceptance of Construction for the Wastewater and Stormwater System Rehabilitation Cured In-Place Pipe (CIPP), Project No. 20021709 and 20021708

 

I.                     RECOMMENDED ACTION

recommendation


Approve the final construction contract with Michels Corporation, of Salem, Oregon for the amount bid including sales tax of $519,488.00, plus change orders and bid item increases and decreases, resulting in a final contract amount of $481,815.60, and accept construction of the Wastewater and Stormwater System Rehabilitation Cured In-Place Pipe (CIPP) Project, Project Nos., 20021709 and 20021708 as of August 21, 2018.

body

II.                     DEPARTMENT CONTACTS

 

Martin Pastucha, Director of Public Works                                                                425-556-2733

Mike Paul, City Engineer                                                                                                          425-556-2721

Joseph O’Leary, Project Manager                                                                                     425-556-2738

 

III.                     DESCRIPTION/BACKGROUND

 

In 2015 and 2016, City maintenance workers conducted video inspections of City wastewater and stormwater pipes. The video inspections revealed that many existing wastewater and stormwater lines were badly deteriorated and in need of rehabilitation. This project successfully rehabilitated over ¾-mile of wastewater pipe and over 1,200 lineal feet of stormwater pipe using a cured-in place pipe trenchless technology. Existing wastewater and stormwater pipes have been restored with a new interior hardened liner that will significantly increases pipe life span.

 

The wastewater fund was under budget in the amount of $42,699, and the stormwater fund was exceeded in the amount of $60,992. The higher stormwater cost was due primarily to a construction change order for using a higher grade of cured in place pipe material that was less harmful to the stormwater environment.

 

 

 

IV.                     PREVIOUS DISCUSSIONS HELD

 

March 13, 2018                     Planning and Public Works Committee

March                      20, 2018                     Award Construction Contract

 

 

V.                     IMPACT

 

A.                     Service/Delivery:

 

The project will greatly reduce the risk of future pipe failure and service disruptions in downtown Redmond.  In addition, it may reduce costly emergency response and repair work.

 

B.                     Fiscal Note:

 

Current Project Budget

Wastewater CIP                                                                                                          $513,733

Stormwater CIP                                                                                                          $263,864

Total Project Budget                                                                                                            $777,597

 

Estimated Project Costs

Design                                                                                                                                                   $158,913

Construction                                                                                                                              $636,977

Total Estimated Project Costs                                                               $795,890

 

Transfer to Wastewater                                                                                    $ 42,699

Transfer from Stormwater                                                                          ($ 60,992)

 

 

VI.                     ALTERNATIVES TO STAFF RECOMMENDATION

 

None

 

VII.                     TIME CONSTRAINTS

 

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon clearances from the Washington State Departments of Revenue and Labor and Industries, with a mandatory 60-day waiting period for filing of claims and liens.

 

VIII.                     LIST OF ATTACHMENTS

 

Attachment A: Vicinity Map