File #: AM No. 18-133   
Type: Consent Item Status: Passed
File created: 7/16/2018 In control: City Council
On agenda: 9/4/2018 Final action: 9/4/2018
Title: Approval of Final Construction Contract in the Amount of $1,630,543.02, with Watson Asphalt Paving Company of Redmond, Washington, and Acceptance of Construction for the 148th Avenue and NE 51st Street Pavement Preservation, Project No. 20011501
Attachments: 1. Agenda Memo No. 18-133, 2. Attachment A: Vicinity Map

MEMO TO:                     Members of the City Council

FROM:                     Mayor John Marchione

SUBJECT:                     


title

Approval of Final Construction Contract in the Amount of $1,630,543.02, with Watson Asphalt Paving Company of Redmond, Washington, and Acceptance of Construction for the 148th Avenue and NE 51st Street Pavement Preservation, Project No. 20011501

 

I.                     RECOMMENDED ACTION

recommendation


Approve the final construction contract with Watson Asphalt Paving Company of Redmond, Washington, for the base bid amount of $1,853,152.90, plus or minus change orders and bid item increases or decreases, resulting in a final contract amount of $1,630,543.02, and accept construction of 148
th Ave NE and NE 51st Street pavement Preservation, Project No. 20011501.

body

II.                     DEPARTMENT CONTACTS

 

Martin Pastucha, Director of Public Works                      425-556-2733

                     Mike Paul, City Engineer                     425-556-2721

Patty S. Criddle, Project Manager                                                                                                          425-556-2736

 

III.                     DESCRIPTION/BACKGROUND

 

Project Purpose

 

These projects will prolong the life of the pavement on:

                     148th Ave NE from the SR 520 Bridge to NE 36th Street and

                     51st Street from 148th Ave NE to NE 51st Street

 

Project Description

 

On both projects, construction began in May 2017 and reached physical completion in November 2017.  The construction timeframe was within the allotted days specified in the contract.

 

Each project rehabilitated approximately one-half (1/2) mile of deteriorating pavement.   Construction on both roadways included:

                     Repairing fatigued pavement areas

                     Constructing curb ramps to current ADA standards

                     Resurfacing the roadway curb to curb with hot mix asphalt

                     Lane rechannelization

                     Signal loop replacements

 

The NE 51st Street project also included:

                     Replacing damaged and deteriorated storm water pipes (funded by Stormwater                      CIP) and

                     Upgrading sanitary sewer manhole lids (funded by Wastewater Operating funds)

 

The final contract amount was less than the bid contract amount due to less than expected utility conflicts and better than anticipated condition of underlying pavement on both 148th Ave NE and NE 51st Street.

 

 

Budget

The City of Bellevue is reimbursing funds to the City of Redmond in the amount of $149,749 for the portion of the work done on 148th Ave NE that is within Bellevue City Limits.  The centerline of 148th Ave NE is the city limit between the City of Redmond and the City of Bellevue, therefore, the southbound lanes of 148th Ave NE within the project limits are in the City of Bellevue.  The City of Bellevue entered into an Interlocal Agency Agreement with the City of Redmond naming the City of Redmond lead agency for the 148th Ave NE Pavement Preservation project.  The City of Redmond administered the design and construction of the improvements along 148th Ave NE and the City of Bellevue has provided matching funds for the design and construction work on 148th Ave NE within the City of Bellevue.

 

 

IV.                     PREVIOUS DISCUSSIONS HELD

 

Council Actions / Communication

 

Date

Action / Committee Presentation

4/08/2014

Review of WSDOT and PSRC (Puget Sound Regional Council) Transportation Grants (Planning/PW Committee Meeting)

9/16/2014

Acceptance of NE 51st St Pavement Preservation Grant

3/10/2015

148th Ave NE Preservation Project, Redmond/Bellevue Interlocal Agreement (Planning/PW Committee Meeting)

3/17/2015

Approval of Redmond/Bellevue Interlocal Agreement for 148th Ave NE Pavement Preservation Project

6/02/2015

Approval of Consultant Agreement with David Evans & Assoc. for 148th Ave NE and NE 51st St Pavement Preservation

5/02/2017

Approve Supplemental Consultant Agreement No. 2

5/02/2017

Award of Bid to Watson Asphalt Paving Company

Today

Accept Construction

 

 

V.                     IMPACT

 

A.                     Service/Delivery:

 

This project resurfaced approximately one (1) mile of arterial streets and constructed curb ramps to current ADA standards.

 

B.                     Fiscal Note:

 

Estimated costs for the project are shown below.

                                          Current Project Budget:

                                          Transportation CIP                     $920,435

                                          148th Ave WSDOT Federal Grant                     $918,000

                                          NE 51st Street WSDOT Federal Grant                     $750,000

                                          City of Bellevue                     $251,536

                                          Stormwater CIP                     $121,040

                                          Wastewater Operating Funds                     $  11,051

                                          Water Operating Funds                                                                                                         $       347

                                          Total Funding                     $2,972,409

                                          Estimated Project Costs:

                                          Design                      Phase                                                                                                                                         $   480,607

                                          Construction                      Phase                                                                                                                    $1,983,592

                                          Total Estimated Project Cost                                                                                               $2,464,199

                                          Budget Difference*                                                                                                                    $   508,210

                                          *Transfer to:

                                          Transportation CIP                                                                                                                       $   309,578

                                          Stormwater CIP                                                                                                                       $     27,665

                                                                                                         

                                          Water Operating Funds                                                                     $       4,315

                                          City of Bellevue                                                                                $   101,787

                                          WSDOT Federal Grant                                                                                               $     64,865

                                          Total                                                                                                                                                               $   508,210 

 

 

VI.                     ALTERNATIVES TO STAFF RECOMMENDATION

 

The Council could choose to not accept the contract.

VII.                     TIME CONSTRAINTS

 

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

VIII.                     LIST OF ATTACHMENTS

 

Attachment A: Vicinity Map