City of Redmond Logo
File #: AM No. 19-094   
Type: Consent Item Status: Passed
File created: 5/1/2019 In control: City Council
On agenda: 6/18/2019 Final action: 6/18/2019
Title: Acceptance of Construction for Mackey Creek Restoration Project with Olson Brothers Excavating, Inc. of Puyallup, Washington, and Approval of the Final Contract in the Amount of $498,622.09, City project No. 20021402
Attachments: 1. Agenda Memo No. 19-094, 2. Attachment A: Vicinity Map
MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:

title
Acceptance of Construction for Mackey Creek Restoration Project with Olson Brothers Excavating, Inc. of Puyallup, Washington, and Approval of the Final Contract in the Amount of $498,622.09, City project No. 20021402


I. RECOMMENDED ACTION
recommendation

Approve the final contract amount with Olson Brothers Excavating, Inc. of Puyallup, Washington, for the base bid amount of $ 537,430, plus or minus change orders and bid items increase or decreases, resulting in a final contract amount of $ 498,622.09 and accept construction of Mackey Creek Restoration project, City project No. 20021402 as of
June 18, 2019.
body

II. DEPARTMENT CONTACTS

Kristi Wilson, Interim Public Works Director 425-556-2733
Tom Hardy, Stream and Habitat Planner 425-556-2762
Bassam Al-Ali, Project Manager 425-556-2743

III. DESCRIPTION/BACKGROUND

Project Purpose

The constructed project provided enhancement to Mackey Creek and its associated riparian and wetland habitat.

This project re-aligned approximately 700 lineal feet of the main stem of Mackey Creek and stabilized the Creek with large woody materials and habitat boulders thus encouraging formation of habitat features along the main stem and throughout the creek.

Project Description

Construction of Mackey Creek project began in August 20, 2018 and was substantially completed on October 22, 2018. Mackey Creek project was under Contract suspension on November 2, 2018 to allow for seed, fertilizer, and mulch work to be done during the allowed working dates for application. Mackey Creek project reached physical completion in April 29, 2019. The construction time frame was within the allotted days specified in the contract.

IV. PREVIOUS DISCUSSIONS HELD

Planning and ...

Click here for full text