File #: AM No. 19-096   
Type: Consent Item Status: Passed
File created: 5/28/2019 In control: City Council
On agenda: 6/18/2019 Final action: 6/18/2019
Title: Award of Bid to Marshbank Construction, Inc. of Lake Stevens, Washington, for the Amount Bid of $4,129,413.48, and Approval of Supplemental Agreement No. 3 with Huitt-Zollars in the Amount of $180,561.18, for NE 51st Street Improvements, and Approval of Supplemental Agreement No. 1, with Huitt-Zollars, in the Amount of $20,264.92, for Additional Design and Construction Support Services for a HAWK Signal, Project Nos. 20021604 and 20021910
Attachments: 1. Agenda Memo No. 19-096, 2. Attachment A: Vicinity Map, 3. Attachment B: Supplemental Consultant Agreement No. 3, 4. Attachment C: Supplemental Consultant Agreement No. 1
MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:

title
Award of Bid to Marshbank Construction, Inc. of Lake Stevens, Washington, for the Amount Bid of $4,129,413.48, and Approval of Supplemental Agreement No. 3 with Huitt-Zollars in the Amount of $180,561.18, for NE 51st Street Improvements, and Approval of Supplemental Agreement No. 1, with Huitt-Zollars, in the Amount of $20,264.92, for Additional Design and Construction Support Services for a HAWK Signal, Project Nos. 20021604 and 20021910


I. RECOMMENDED ACTION
recommendation

Award the bid for the NE 51st Street Improvements, City Project No. 20021604, to Marshbank Construction, Inc. of Lake Stevens, Washington, for the amount bid of $4,129,413.48, and authorize the Mayor to sign the contract. Approve Supplemental Agreement No. 3 (NE 51st Improvements) with Huitt-Zollars for $180,561.18 and Supplemental Agreement No. 1 (HAWK Signal) for $20,264.92 for additional design and construction support services and authorize the Mayor to sign the agreements.
body

II. DEPARTMENT CONTACTS

Maxine Whattam, Interim Public Works Director 425-556-2710
Gary Schimek, City Engineer 425-556-2742
Eric Dawson, Project Manager 425-556-2867

III. DESCRIPTION/BACKGROUND

The purpose of this project is to increase vehicular, bicycle, and pedestrian capacity and safety on NE 51st Street between the westbound SR 520 intersection and 156th Avenue NE. The project will also provide a new pedestrian crossing on 156th Avenue NE at the 4800 block near the Onyx Apartments driveway, location of two Metro Transit stops.

Background

The NE 51st Street project includes adding turn lanes at both 154th Avenue NE and 156th Avenue NE, and bicycle lanes from the vicinity of the eastbound SR 520 ramps to 154th Avenue NE, funded by the CFD 2016-1. Pedestrian safety improvements at the westbound 520 intersection with NE 51st Street will also be constructed, funded by the Washington...

Click here for full text