MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:
title
Acceptance of Construction for the SR 520 NE 40th and 51st Street Eastbound Collector-Distributor Ramp Modification with McCann Construction Enterprises, Inc. of Renton, Washington, and Approval of Final Contract in the Amount of $1,080,925.03, Project No. 20021605
I. RECOMMENDED ACTION
recommendation
Approve the final contract amount with McCann Construction Enterprises, Inc. of Renton, Washington, for the base bid amount of $1,154,791.00, plus or minus change orders and bid items increases or decreases, resulting in a final contract amount of $1,080,925.03, and accept construction of SR 520 NE 40th and 51st Street Eastbound Collector-Distributor Ramp Modification, Project No. 20021605, as of December 3, 2019.
body
II. DEPARTMENT CONTACTS
Dave Juarez, Director of Public Works 425-556-2733
Gary Schimek, Interim City Engineer 425-556-2742
John Mork, Project Manager 425-556-2713
III. DESCRIPTION/BACKGROUND
Project Purpose
The purpose of this project was to improve safety and reduce congestion by splitting the Eastbound SR 520 combined exit ramp at 40th and 51st Streets into two separate off ramps. This project reduced queuing on the SR 520 mainline, particularly during AM peak hours.
Project Description
A portion of the existing concrete barriers between the Eastbound 520 mainline and the 40th Street/51st Street Collector-Distributor (C-D) was removed and replaced with a new 51st Street exit. Work also included revisions to channelization, signage, and storm drainage.
Background
Ramp Split
The Eastbound SR 520 40th/51st ramp split concept is similar to the Westbound SR 520 40th/51st ramp split that was completed in 2015. That project successfully reduced congestion compared to the original combined ramp exit.
WSDOT and Redmond staff modeled implementation of a similar project to split the Eastbound 520 40th/51st combined ramp exit and found similar congestion reduction benefits. Washington State is providing most of the funding for this project via the Connecting Washington transportation package.
Connecting Washington Funding
The 2015 Connecting Washington transportation package provided $5 million dollars towards investments in the Overlake area. Council authorized use of a portion of these funds to design four projects. This project package includes:
-
1. |
Eastbound SR520 40th/51st Ramp Split |
City to construct |
Complete |
2. |
Pedestrian safety improvements @ SR520 on/off-ramp intersections @ 40th Eastbound |
Sound Transit to construct |
Complete in May 2022 |
3. |
Pedestrian safety improvements @ SR520 on/off-ramp intersections @ 51st Eastbound |
Sound Transit to construct |
Complete in June 2021 |
4. |
Pedestrian safety improvement @ SR520 on/off-ramp intersections @ 51st Westbound |
City to construct |
Currently underway |
All four projects were originally anticipated to be designed and constructed together on the same schedule. However, design of the Eastbound SR 520 40th/51st Ramp Split was completed in advance of the other projects and was ready to move forward and provide
mobility benefits now.
Redmond managed the design and construction for the Eastbound 520 40th/51st ramp split project utilizing Washington State funds.
IV. PREVIOUS DISCUSSIONS HELD
Date |
Action / Committee Presentation |
03/08/2016 |
Planning and Public Works Committee/ Improvements in the SR 520 Area Around 40th and 51st Streets |
07/12/2016 |
Planning and Public Works Committee |
07/19/2016 |
Approve Consultant Agreement |
02/06/2018 |
Approve Supplemental Consultant Agreement No. 1 |
06/19/2018 |
Award of Bid |
06/19/2018 |
Approve Supplemental Consultant Agreement No. 2 |
Today |
Accept Construction |
V. IMPACT
A. Service/Delivery:
Provide a new exit from Eastbound SR 520 directly to 51st Street. This reduced queuing on the Eastbound SR 520 mainline that previously occurred during AM peak hours. Completion in advance of major construction projects in the Overlake Neighborhood will provide more route options and may reduce construction impacts on travel.
B. Fiscal Note:
Current Project Budget:
Connection WA Funding $1,981,085
Transportation CIP $50,000
Total Funding $2,031,085
Estimated Project Costs:
Design Phase $910,652*
Construction Phase $1,320,433
Total Estimated Project Cost $2,231,085
Budget Difference Transportation CIP ($200,000)**
**Transfer from Transportation CIP $200,000
Connecting WA Balance:
Connecting WA Funding |
$5,000,000 |
Eastbound SR520 40th/51st Ramp Split |
$1,981,085 |
Pedestrian safety improvement @ SR520 on/off-ramp intersections @ 51st Westbound |
$ 805,723 |
Balance |
$2,231,085** |
*Design amount is for varying levels of design on all four Connecting WA projects.
**Working with WSDOT to move remaining balance to the 40th Street grade Separation
VI. ALTERNATIVES TO STAFF RECOMMENDATION
None
VII. TIME CONSTRAINTS
Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.
VIII. LIST OF ATTACHMENTS
A. Vicinity Map