City of Redmond Logo
File #: AM No. 19-181   
Type: Consent Item Status: Passed
File created: 11/5/2019 In control: City Council
On agenda: 12/3/2019 Final action: 12/3/2019
Title: Acceptance of Construction for the SR 520 NE 40th and 51st Street Eastbound Collector-Distributor Ramp Modification with McCann Construction Enterprises, Inc. of Renton, Washington, and Approval of Final Contract in the Amount of $1,080,925.03, Project No. 20021605
Attachments: 1. Agenda Memo No. 19-181, 2. Attachment A: Vicinity Map

MEMO TO:                     Members of the City Council

FROM:                     Mayor John Marchione

SUBJECT:                     


title

Acceptance of Construction for the SR 520 NE 40th and 51st Street Eastbound Collector-Distributor Ramp Modification with McCann Construction Enterprises, Inc. of Renton, Washington, and Approval of Final Contract in the Amount of $1,080,925.03, Project No. 20021605

 

I.                     RECOMMENDED ACTION

recommendation


Approve the final contract amount with McCann Construction Enterprises, Inc. of Renton, Washington, for the base bid amount of $1,154,791.00, plus or minus change orders and bid items increases or decreases, resulting in a final contract amount of $1,080,925.03, and accept construction of SR 520 NE 40
th and 51st Street Eastbound Collector-Distributor Ramp Modification, Project No. 20021605, as of December 3, 2019.

body

II.                     DEPARTMENT CONTACTS

 

Dave Juarez, Director of Public Works                                                                                                         425-556-2733

                     Gary Schimek, Interim City Engineer                                                                                                         425-556-2742

John Mork, Project Manager                                                                                                                                                   425-556-2713

 

III.                     DESCRIPTION/BACKGROUND

 

Project Purpose

The purpose of this project was to improve safety and reduce congestion by splitting the Eastbound SR 520 combined exit ramp at 40th and 51st Streets into two separate off ramps.  This project reduced queuing on the SR 520 mainline, particularly during AM peak hours.

 

Project Description

A portion of the existing concrete barriers between the Eastbound 520 mainline and the 40th Street/51st Street Collector-Distributor (C-D) was removed and replaced with a new 51st Street exit. Work also included revisions to channelization, signage, and storm drainage.

 

Background

 

Ramp Split

The Eastbound SR 520 40th/51st ramp split concept is similar to the Westbound SR 520 40th/51st ramp split that was completed in 2015.  That project successfully reduced congestion compared to the original combined ramp exit.

 

WSDOT and Redmond staff modeled implementation of a similar project to split the Eastbound 520 40th/51st combined ramp exit and found similar congestion reduction benefits. Washington State is providing most of the funding for this project via the Connecting Washington transportation package.

 

Connecting Washington Funding

The 2015 Connecting Washington transportation package provided $5 million dollars towards investments in the Overlake area. Council authorized use of a portion of these funds to design four projects. This project package includes:

-                     

1.

Eastbound SR520 40th/51st Ramp Split

City to construct

Complete

2.

Pedestrian safety improvements @ SR520 on/off-ramp intersections @ 40th Eastbound

 Sound Transit to construct

 Complete in May 2022

3.

Pedestrian safety improvements @ SR520 on/off-ramp intersections @ 51st Eastbound

 Sound Transit to construct

Complete in June 2021

4.

Pedestrian safety improvement @ SR520 on/off-ramp intersections @ 51st Westbound

 City to construct

 Currently underway

 

All four projects were originally anticipated to be designed and constructed together on the same schedule. However, design of the Eastbound SR 520 40th/51st Ramp Split was completed in advance of the other projects and was ready to move forward and provide

mobility benefits now.

 

Redmond managed the design and construction for the Eastbound 520 40th/51st ramp split project utilizing Washington State funds.

 

IV.                     PREVIOUS DISCUSSIONS HELD

 

 

Date

Action / Committee Presentation

03/08/2016

Planning and Public Works Committee/ Improvements in the SR 520 Area Around 40th and 51st Streets

07/12/2016

Planning and Public Works Committee

07/19/2016

Approve Consultant Agreement

02/06/2018

Approve Supplemental Consultant Agreement No. 1

06/19/2018

Award of Bid

06/19/2018

Approve Supplemental Consultant Agreement No. 2

Today

Accept Construction

 

V.                     IMPACT

 

A.                     Service/Delivery:

 

Provide a new exit from Eastbound SR 520 directly to 51st Street. This reduced queuing on the Eastbound SR 520 mainline that previously occurred during AM peak hours.  Completion in advance of major construction projects in the Overlake Neighborhood will provide more route options and may reduce construction impacts on travel. 

 

B.                     Fiscal Note:

 

Current Project Budget:

Connection WA Funding                     $1,981,085

Transportation CIP                         $50,000

Total Funding                     $2,031,085

Estimated Project Costs:

Design Phase                     $910,652*

Construction Phase                     $1,320,433

Total Estimated Project Cost                     $2,231,085

Budget Difference Transportation CIP                     ($200,000)**

**Transfer from Transportation CIP                     $200,000

Connecting WA Balance:

Connecting WA Funding

$5,000,000

Eastbound SR520 40th/51st Ramp Split

$1,981,085

Pedestrian safety improvement @ SR520 on/off-ramp intersections @ 51st Westbound

$   805,723

Balance

$2,231,085**

*Design amount is for varying levels of design on all four Connecting WA projects.

**Working with WSDOT to move remaining balance to the 40th Street grade Separation

VI.                     ALTERNATIVES TO STAFF RECOMMENDATION

 

None

 

VII.                     TIME CONSTRAINTS

 

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

VIII.                     LIST OF ATTACHMENTS

 

A.                     Vicinity Map