City of Redmond Logo
File #: AM No. 20-129   
Type: Consent Item Status: Passed
File created: 9/16/2020 In control: City Council
On agenda: 10/6/2020 Final action: 10/6/2020
Title: Redmond 2050: Resolution adopting the Scope, Timeline, and Public Involvement Plan a. Resolution No. 1538: A Resolution Establishing the Scope, Timeline, and Community Involvement Plan for the 2050 Periodic Review and Update of the Redmond Comprehensive Plan
Attachments: 1. Agenda Memo, 2. Attachment A: Resolution, 3. Attachment B: Resolution Exhibit 1 - Scope and Timeline, 4. Attachment C: Resolution Exhibit 2 – Community Involvement Plan

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Planning and Community Development

Beverly Mesa-Zendt

Interim Deputy Director

 

 

TITLE:

title

Redmond 2050: Resolution adopting the Scope, Timeline, and Public Involvement Plan

a.                     Resolution No. 1538: A Resolution Establishing the Scope, Timeline, and Community Involvement Plan for the 2050 Periodic Review and Update of the Redmond Comprehensive Plan

 

OVERVIEW STATEMENT:

recommendation

Staff will be seeking approval of the Redmond 2050 scope, timeline, and Community Involvement Plan in accordance with the requirements set forth in RCW36.70A.130 <http://app.leg.wa.gov/RCW/default.aspx?cite=36.70A.130> and RCW36.70A.140 <http://app.leg.wa.gov/RCW/default.aspx?cite=36.70A.140>.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Redmond Comprehensive Plan and implementing plans, policies, and regulations.

                     Required:

Washington State Growth Management Act requires that each Washington city and county periodically review and, if needed, revise its comprehensive plan and development regulations every eight years.  For King County and all cities within King County, the “periodic review” must be completed by June 30, 2024, per WAC 365-196-610.  A resolution adopting the scope, timelines, and public involvement plan is required.

                     Council Request:

N/A

                     Other Key Facts:

State law requires that each city, proposing amendments to their comprehensive plan, establish a public participation program identifying procedures for early and continuous public involvement in the development and amendment of comprehensive land use plans and development regulations implementing such plans.  The public participation program should inform the public of when to comment on proposed changes to the plan, identify the scope and timeline for the review and identify dates for anticipated legislative action.  Notice of updates must be provided in accordance with RCW 36.70A.035.  In addition to the published notice of this resolution, scope, timeline, and Community Involvement Plan, staff will be posting all documents and updates to the Redmond 2050 project page at www.Redmond.gov/Redmond2050 <http://www.Redmond.gov/Redmond2050>

 

Staff is requesting approval of the resolution provided for in Attachment A

 

 

OUTCOMES:

Adoption of the resolution for the periodic review and update of the Comprehensive Plan will advance public understanding and awareness of the periodic review of the Comprehensive Plan (Redmond 2050); facilitate greater participation, and ensure compliance with state law.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

A full project scope and timeline is provided in Attachment B.

                     Outreach Methods and Results:

The full Community Involvement Plan for Phase 1 is provided in Attachment C.  Updates, details, and a plan for Phase 2 will be posted online at www.Redmond.gov/Redmond2050 <http://www.Redmond.gov/Redmond2050>.

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

N/A - no cost for the Resolution

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

N/A

 

Budget Priority:

Vibrant Economy

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

On August 18, 2020, the City Council approved contracts with IBI Group (Community Visioning) and BERK Consulting (Environmental Analysis).  The total contract amount of $480,000 will be spent over multiple years.  The $218,000 of funding required for 2020 is budgeted in the current biennium and the remaining amount, obligated for 2021-2022, will be carried forward into the next biennial budget.

 

Funding source(s):

General Fund

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

5/19/2020

Business Meeting

Provide Direction

9/8/2020

Committee of the Whole - Planning and Public Works

Provide Direction

9/15/2020

Business Meeting

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

 

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Council may consider and recommend changes to the scope, timeline, and community involvement plan.

 

 

ATTACHMENTS:

Attachment A - Resolution

Attachment B - Resolution Exhibit 1 - Scope and Timeline

Attachment C - Resolution Exhibit 2 - Community Involvement Plan