File #: CM 21-111   
Type: Committee Memo Status: Presented
File created: 3/30/2021 In control: City Council
On agenda: 4/6/2021 Final action: 4/6/2021
Title: Westside Park Renovation Bids
Attachments: 1. Agenda Memo

TO: Committee of the Whole - Parks and Human Services

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Carrie Hite

425-556-2326

 

DEPARTMENT STAFF:

Parks

Jeff Aken

Senior Planner

Public Works

Rob Crittenden

Senior Engineer

 

 

TITLE:

title

Westside Park Renovation Bids

 

OVERVIEW STATEMENT:

recommendation

Westside Park is a 47-year-old neighborhood park in the Overlake Neighborhood which was last renovated in 1991.  The purpose of this project is to upgrade the Park to improve play field drainage, construct a new playground and sport court, and install a paved path looping through the Park. 

 

Staff received 3 bids on March 25, 2021 to construct the project and is working on certifying the low bid.  Staff will be prepared to bring the award of bid forward for Council approval on April 20, 2021.

 

A supplemental consultant agreement with Board & Vellum Architects is needed so they can provide services to the City during construction including submittal review, response to questions from the contractor, and assistance with change orders as needed.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Westside Park Master Plan, PARCC Plan

                     Required:

Council approval is required to award a construction contract over $300,000 per 2018 City Resolution 1503.

Revised Code of Washington 39.80 and City Purchasing Policies and Procedures requires Council authorization for the Mayor to sign the consultant agreement.

                     Council Request:

N/A

                     Other Key Facts:

Board & Vellum Architects - Contract Summary

                     Consultant Agreement on 10/11/2019

o                     Amount $493,103

o                     Completion date 12/31/2020

                     Supplemental Agreement 1 on 11/3/2020

o                     Extended completion date to 12/31/2021

                     Supplemental Agreement 2 pending Council approval

o                     Amount $100,000

o                     Extends completion date to 12/31/2022

                     Total Cost for All $593,103

 

 

OUTCOMES:

The overall park project will increase the parks use and community benefit by making it useable year around with picnic shelter, pathways, improved drainage and nature play elements.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Community Outreach for the Westside Park Master plan occurred in three open houses in late 2019 and early 2020 which helped define the layout of the Park

 

                     Outreach Methods and Results:

Survey of community asking for preferred outcomes

                     Feedback Summary:

The community was interested in seeing nature play, trail connections/wayfinding, improved sports court and a more useable lawn area. 

 

 

BUDGET IMPACT:

 

Total Cost:

$2.6M

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

Part of the Healthy and Sustainable area in the Capital Improvement Program, Map #137, Overlake Investments.

 

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Parks CIP

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

1/4/2021

Committee of the Whole - Parks and Human Services

Receive Information

3/24/2020

Study Session

Receive Information

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

4/20/2021

Business Meeting

Approve

 

Time Constraints:

Staff will bring contract to City Council on April 20, 2021 in order to start construction in late spring of 2021.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If the City Council chooses not to award the bid for this contract on April 20, 2021. it will delay construction of the project to the summer of 2022.  The cost to construct next year would likely be higher.

 

 