File #: AM No. 21-103   
Type: Consent Item Status: Passed
File created: 7/6/2021 In control: City Council
On agenda: 7/20/2021 Final action: 7/20/2021
Title: Approval of the Final Contract with Marshbank Construction, Inc. of Lake Stevens, WA for the Base Bid Amount of $4,129,413, Plus or Minus Change Orders and Bid Items Increases or Decreases, Resulting in a Final Contract Amount of $4,144,039, and Accept Construction of NE 51ST Street Improvements, Project No. 20021604 and 20021910
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Dave Juarez

425-556-2733

 

DEPARTMENT STAFF:

Public Works

Eric Dawson

Senior Engineer

 

 

TITLE:

title

Approval of the Final Contract with Marshbank Construction, Inc. of Lake Stevens, WA for the Base Bid Amount of $4,129,413, Plus or Minus Change Orders and Bid Items Increases or Decreases, Resulting in a Final Contract Amount of $4,144,039, and Accept Construction of NE 51ST Street Improvements, Project No. 20021604 and 20021910

 

OVERVIEW STATEMENT:

recommendation

The project increased vehicular, bicycle, and pedestrian capacity and safety on NE 51st Street between the westbound SR 520 intersection and 156th Avenue NE.  The project also provided a new pedestrian crossing on 156th Avenue NE at the 4800 block near the Onyx Apartments driveway, location of two Metro Transit stops.​

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

​Transportation CIP​

                     Required:

Council approval is required to accept a construction contract over $300,000 per 2018 City Resolution 1503.

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Improved safety and capacity for vehicles, pedestrians, and bicycles on NE 51st Street and 156th Avenue NE.

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

Regular coordination occurs with local businesses in the area and business representatives were invited to the project’s weekly coordination meeting.  Homeowners in the project vicinity were mailed a post card with project details and the project manager’s contact information prior to construction.

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

​Total Estimated Project Cost: $6,663,045

Approved Budget Amount: $7,348,017

Remaining funds will be transferred back to the Community Facilities District No. 2016-1​

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

2019-2020 CIP

 

Budget Priority:

Infrastructure

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Transportation CIP

Community Facilities District No. 2016-1

Connecting Washington Grant

Transportation Improvement Board Grant

 

Budget/Funding Constraints:

Warranty start date is based on Council acceptance

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/18/2019

Business Meeting

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Warranty start date is based on Council acceptance​

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Delay in Warranty start and increased project cost due to longer close out

 

 

ATTACHMENTS:

Attachment A - Vicinity Map