Title: Approve General Services Agreement with Technical Systems Inc. (TSI) in the Amount of $3,581,143 for the Telemetry System Upgrade, Phases 2 and 3 Project and increase the total funding for this Project from $2,445,000 to $5,205,057 from the Water CIP
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map, 3. Attachment B: Additional Project Information, 4. Attachment C: TSI General Services Agreement, 5. Attachment D: BHC Email RE: TSI Cost Proposal

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2880

 

DEPARTMENT STAFF:

Public Works

Mike Haley

Project Manager

Public Works

Steve Hitch

Engineering Supervisor

Public Works

Jon Spangler

Engineering Manager

 

 

TITLE:

title

Approve General Services Agreement with Technical Systems Inc. (TSI) in the Amount of $3,581,143 for the Telemetry System Upgrade, Phases 2 and 3 Project and increase the total funding for this Project from $2,445,000 to $5,205,057 from the Water CIP

 

OVERVIEW STATEMENT:

recommendation

This sole-source contract with TSI is to refurbish or replace control panels and communication systems at 12 of the city water facilities.  This includes five flow control sites, four tank sites, and three well sites.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Approving this action keeps the City on the path to completing Phases 2 and 3 of the Telemetry Upgrade projects, which will improve the safety and reliability of the City’s water system.

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$3,581,143

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

Staff are requesting an additional $2,760,057 to complete the project.

 

Funding source(s):

Water CIP

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/7/2022

Committee of the Whole - Planning and Public Works

Provide Direction

 

 

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Approval of the general services agreement in June of 2022 will likely allow for timely completion of Telemetry Upgrade Phase 2 and 3 before any older components fail.  The project is scheduled to begin in July of 2022 and will require two years to complete.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Delay of this upgrade could result in aging equipment failures that would disrupt operation of the water system.  Should our existing, older equipment fail it may not be easily replaced due to availability of spares.

 

 

ATTACHMENTS:

Attachment A: Vicinity Map

Attachment B: Additional Project Information

Attachment C: TSI General Services Agreement

Attachment D: BHC email RE: TSI cost proposal