File #: CM 21-111   
Type: Committee Memo Status: Presented
File created: 3/30/2021 In control: City Council
On agenda: 4/6/2021 Final action: 4/6/2021
Title: Westside Park Renovation Bids
Attachments: 1. Agenda Memo
TO: Committee of the Whole - Parks and Human Services
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Parks
Carrie Hite
425-556-2326

DEPARTMENT STAFF:
Parks
Jeff Aken
Senior Planner
Public Works
Rob Crittenden
Senior Engineer


TITLE:
title
Westside Park Renovation Bids


OVERVIEW STATEMENT:
recommendation
Westside Park is a 47-year-old neighborhood park in the Overlake Neighborhood which was last renovated in 1991. The purpose of this project is to upgrade the Park to improve play field drainage, construct a new playground and sport court, and install a paved path looping through the Park.

Staff received 3 bids on March 25, 2021 to construct the project and is working on certifying the low bid. Staff will be prepared to bring the award of bid forward for Council approval on April 20, 2021.

A supplemental consultant agreement with Board & Vellum Architects is needed so they can provide services to the City during construction including submittal review, response to questions from the contractor, and assistance with change orders as needed.

body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Westside Park Master Plan, PARCC Plan
* Required:
Council approval is required to award a construction contract over $300,000 per 2018 City Resolution 1503.
Revised Code of Washington 39.80 and City Purchasing Policies and Procedures requires Council authorization for the Mayor to sign the consultant agreement.
* Council Request:
N/A
* Other Key Facts:
Board & Vellum Architects - Contract Summary
* Consultant Agreement on 10/11/2019
o Amount $493,103
o Completion date 12/31/2020
* Supplemental Agreement 1 on 11/3/2020
o Extended completion date to 12/31/2021
* Supplemental Agreement 2 pending Council approval
o Amount $100,000
o Extends completion date to 12/31/2022
* Total Cost for All $593,103


OUT...

Click here for full text