Title: Approval of Consultant Agreement with BHC Consultants, L.L.C. in the Amount of $912,000 for Design and Construction Services for Wastewater Pump Station No. 13 Replacement, Project No. 20021809
Attachments: 1. Agenda Memo No. 18-137, 2. Attachment A: Vicinity Map, 3. Attachment B: Agreement
MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:

title
Approval of Consultant Agreement with BHC Consultants, L.L.C. in the Amount of $912,000 for Design and Construction Services for Wastewater Pump Station No. 13 Replacement, Project No. 20021809


I. RECOMMENDED ACTION
recommendation

Approve the consultant agreement with BHC Consultants, L.L.C. in the amount of $912,000 for design and construction services for Wastewater Pump Station No. 13 Replacement, Project No. 20021809, and authorize the Mayor to sign the agreement.
body

II. DEPARTMENT CONTACTS

Martin Pastucha, Director of Public Works 425-556-2733
Mike Paul, City Engineer 425-556-2721
Mike Haley, Project Manager 425-556-2843

III. DESCRIPTION/BACKGROUND

Project Purpose
The City has identified Wastewater Pump Station No. 13 is in need of replacement as a part of the Capital Improvement Program.

Project Background
Wastewater Pump Station No. 13 was built in 1985 to provide wastewater conveyance for a large area of the Marymoor Business Park. The existing station age and equipment are beyond their useful life and need to be replaced. The pump station has been scheduled for rehabilitation in the Wastewater CIP.

In 2017, the Marymoor Subarea (Business Park) was rezoned from light industrial to a combination of multi-family and commercial. The new zoning requires the pump station system capability to be increased from 675 gallons per minute to a size capable of pumping 2,000 gallons per minute peak wastewater flow. The new wastewater pump system is scheduled to be complete before flows from the rezoned area exceed the capacity of the existing wastewater pump system.

Project Description
This project will design a replacement for Wastewater Pump Station No. 13 with a new station capable of pumping 2,000 gallons per minute of wastewater into a new 12-inch force main along 176th Ave NE and NE 70th St that will discharge to the King County wastewater col...