City of Redmond Logo
File #: AM No. 18-182   
Type: Consent Item Status: Passed
File created: 10/24/2018 In control: City Council
On agenda: 12/4/2018 Final action: 12/4/2018
Title: Approval of Final Construction Contract in the Amount of $280,292.17, with Northwest Relining, LLC, of Olympia, Washington, and Acceptance of Construction for 152nd Westpark and 90th Street Storm Improvements, Project No. 20021318
Attachments: 1. Agenda Memo No. 18-182, 2. Attachment A: Vicinity Map
MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:

title
Approval of Final Construction Contract in the Amount of $280,292.17, with Northwest Relining, LLC, of Olympia, Washington, and Acceptance of Construction for 152nd Westpark and 90th Street Storm Improvements, Project No. 20021318


I. RECOMMENDED ACTION
recommendation

Approve the final construction contract with Northwest Relining, LLC, of Olympia, Washington for the amount bid including sales tax of $319,640.10, plus change orders and bid item increases and decreases, resulting in a final contract amount of $280,292.17, and accept construction of the 152nd Westpark and 90th St Storm Improvements, Project
No. 20021318.
body

II. DEPARTMENT CONTACTS

Martin Pastucha, Director of Public Works 425-556-2733
Mike Paul, City Engineer 425-556-2721
Joseph O'Leary, Project Manager 425-556-2738


III. DESCRIPTION/BACKGROUND

The stormwater lines located in the right of way of 152nd Ave NE adjacent to Westpark Business Park were in a state of disrepair. City maintenance crews had identified these pipes for replacement based on field pipe inspection and video recordings. The existing corrugated metal pipes were heavily corroded and large tree roots had entered the pipes obstructing water flow during storm events. After evaluating options for replacing the pipes, it was determined that least expensive and less obtrusive construction approach was to slip line the existing pipe with new pipe. The work has been successfully completed and the new pipe installation is now allowing stormwater to freely flow.

On NE 90th Street, east of 160th Ave NE, there was a large existing perforated stormwater infiltration pipe. The large pipe was designed and installed with perforations prior to the existence of the wellhead protection zone. This pipe was found to be a good candidate for slip lining to ensure the integrity of the pipe. The slip line pipe has been installed...

Click here for full text