File #: AM No. 19-089   
Type: Consent Item Status: Passed
File created: 3/13/2019 In control: City Council
On agenda: 6/4/2019 Final action: 6/4/2019
Title: Approval of a Consultant Agreement with RH2 Engineering, in an Amount Not-to-Exceed $247,761, for the 10000 Block of Avondale Erosion at Bear Creek, Project No. 20021807
Attachments: 1. Agenda Memo No. 19-089, 2. Attachment A: Vicinity Map and Photos, 3. Attachment B: Consultant Agreement
MEMO TO: Members of the City Council
FROM: Mayor John Marchione
SUBJECT:

title
Approval of a Consultant Agreement with RH2 Engineering, in an Amount Not-to-Exceed $247,761, for the 10000 Block of Avondale Erosion at Bear Creek, Project No. 20021807


I. RECOMMENDED ACTION
recommendation

Approve a consultant agreement with RH2 Engineering for alternatives analysis, preliminary design, and permitting services for the 10000 Avondale Road Erosion at Bear Creek, Project No. 20021807, in an amount not-to-exceed $247,761 and authorize the Mayor to sign the Agreement. Authorize staff to secure property rights necessary to construct and maintain the project.
body

II. DEPARTMENT CONTACTS

Kristi Wilson, Interim Public Works Director 425-556-2529
Gary Schimek, P.E., EUSD Manager 425-556-2742
Emily Flanagan, P.E., Functional Area Lead PW / EUSD 425-556-2707
Adnan Shabir, P.E., Project Manager PW 425-556-2724

III. DESCRIPTION/BACKGROUND

Bear Creek is migrating into the Avondale Road roadway embankment north of Novelty Hill Road. Significant erosion has occurred at the slope toe, causing settlement of the embankment and resulting in minor sidewalk undercutting. The creek migration has also damaged two stormwater outfalls. It is estimated that the creek has laterally migrated about 90 feet from its 1936 location.
Bear Creek is a critical part of WRIA8's Chinook Recovery plan, so one of this project's primary focus will need to be improving the instream habitat of this reach. The project has the dual purpose of repairing the Avondale Road embankment and providing an environmental improvement to Bear Creek.
Because of this dual goal, the project will be funded by both Transportation and the Stormwater Capital Improvement Program budgets. Funding has been budgeted in the CIP for design and construction.
Process to Date
* The erosion was identified by City staff in 2017. In the Spring of 2018 a consultant team was hired under the On-Call...