File #: AM No. 21-075-1   
Type: New Business Status: Passed
File created: 5/6/2021 In control: City Council
On agenda: 6/15/2021 Final action: 6/15/2021
Title: Approval of the 170th Ave NE Road Closure for Penny Lane Development Sewer Line Work
Attachments: 1. Agenda Memo, 2. Attachment A: 170th Ave NE Closure and Detour, 3. Attachment B: Vicinity Map
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Dave Juarez
425-556-2733
Planning and Community Development
Carol Helland
425-556-2107

DEPARTMENT STAFF:
Planning and Community Development
Jason Lynch
Assistant Director of Development Services
Planning and Community Development
Joe Johnson
Construction Inspection Supervisor
Public Works
Paul Cho
Traffic Operations Manager
Public Works
Adnan Shabir
Senior Engineer


TITLE:
title
Approval of the 170th Ave NE Road Closure for Penny Lane Development Sewer Line Work

OVERVIEW STATEMENT:
recommendation
Penny Lane is Private Development townhome construction project adjacent to 170th Ave NE. As part of the project, improvements in the roadway include an update to the sewer line on 170th Ave NE. The sewer line is situated in the middle of the roadway and requires deep excavation. The Contractor was given approval by City Council to close the roadway in lieu of using steel trench plates.

We are currently seeking an extension of the previously approved road closure for the Penny Lane project as the work is taking longer than originally planned. The approved road closure expires Friday, June 11th. The sandy soils are creating sluff, which is slowing the current process, the contractor has an additional 200 feet of sewer line to install and are expecting construction to take an additional 20-25 days to complete.
Construction activity would take place between 7AM-7PM Monday through Friday with potential of Saturday work. Approval for full road closures is required from Council per RMC 10.24.047.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve

REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
Council approval is required for full road closures per RMC 10.24.047
* Council Request:
N/A
* Other Key Facts:
The Contractor is currently performing th...

Click here for full text