Title: Award of Bid for the Wastewater Pump Station No. 13 Rehabilitation to Harbor Pacific Contractors, in the Amount of $9,487,500; Approval of Supplemental Agreement No. 1 with BHC Consultants for Construction Support Services in an Amount Not-to-Exceed $479,000; and Approval of Supplemental Agreement No. 1 with OTAK for On-Call Construction Management and Inspection Support Services in an Amount Not-to-Exceed $1,000,000, Project No. 20021809
Attachments: 1. Agenda Memo No. 20-038, 2. Attachment A: Location Map, 3. Attachment B: BHC Supplemental Agreement, 4. Attachment C: OTAK Supplemental Agreement, 5. Attachment D: Pump Station Program Update

MEMO TO: Members of the City Council
FROM: Mayor Angela Birney
SUBJECT:

title
Award of Bid for the Wastewater Pump Station No. 13 Rehabilitation to Harbor Pacific Contractors, in the Amount of $9,487,500; Approval of Supplemental Agreement No. 1 with BHC Consultants for Construction Support Services in an Amount Not-to-Exceed $479,000; and Approval of Supplemental Agreement No. 1 with OTAK for On-Call Construction Management and Inspection Support Services in an Amount Not-to-Exceed $1,000,000, Project No. 20021809


I. RECOMMENDED ACTION
recommendation

Award the bid for the Wastewater Pump Station No. 13 Rehabilitation, City Project No. 20021809, to Harbor Pacific Contractors, Inc. of Woodinville, WA for the amount bid of $9,487,500, and authorize the Mayor to sign the contract.

Approve the Supplemental Consultant Agreement No. 1 with BHC Consultants, LLC for construction support services for Wastewater Pump Station No. 13 Replacement in an amount not exceed $479,000 and authorize the Mayor to sign the agreements.

Approve the Supplemental Consultant Agreement No. 1 with OTAK for on call construction management and inspection support services related to wastewater pump stations in an amount not to exceed $1,000,000 and authorize the Mayor to sign the agreement.

body

II. DEPARTMENT CONTACTS

Dave Juarez, Director of Public Works 425-556-2733
Gary Schimek, Acting City Engineer 425-556-2742
Mike Haley, Project Manager 425-556-2843

III. DESCRIPTION/BACKGROUND

Project Purpose
The City has identified Wastewater Pump Station 13 for rehabilitation as a part of the City Council adopted 2019-2020 Capital Improvement Program.



Project Background
The 2019-2020 Wastewater CIP includes several projects to replace or abandon wastewater pump stations due to aging and failing equipment. Wastewater Pump Station 13 was built in 1985 to provide wastewater conveyance for a large area of the Marymoor Business Park. The existing station's equ...