Title: 10000 Avondale Final Design and Construction Consultant Agreement
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map, 3. Attachment B: Preferred Alternative, 4. Attachment C: Consultant Agreement Supplement, 5. Attachment D: Project Cost
TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Dave Juarez
425-556-2733

DEPARTMENT STAFF:
Public Works
Aaron Noble
Project Manager
Public Works
Emily Flanagan
Senior Surface Water Engineer

TITLE:
title
10000 Avondale Final Design and Construction Consultant Agreement

OVERVIEW STATEMENT:
recommendation
This agreement authorizes the consultant, RH2 Engineering, to begin Final Design and Services during Construction for the 10000 Block of Avondale Erosion Control Project.
body

? Additional Background Information/Description of Proposal Attached

REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve

REQUEST RATIONALE:
* Relevant Plans/Policies:
N/A
* Required:
N/A
* Council Request:
N/A
* Other Key Facts:
Council approval is required to continue design

OUTCOMES:
The primary purpose of this project is to rebuild/reinforce the embankment to protect Avondale Road while providing an environmental lift of Bear Creek within the project limits.

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
Planned: 100% Design July 2021, Construction February 2022
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A



BUDGET IMPACT:
Total Cost: RH2 Final Design and Construction Services: $349,952
Total Cost of the Project: $2,269,458

Approved in current biennial budget: ? Yes ? No ? N/A

Budget Offer Number:
00169
00117

Budget Priority:

Infrastructure

Other budget impacts or additional costs: ? Yes ? No ? N/A
If yes, explain:
N/A

Funding source(s):
Stormwater CIP: $733,458
Transportation CIP: $436,000
King County Flood Control District CIP: $1,100,000

Budget/Funding Constraints:
Future Council Actions include acceptance of the King County Flood Control District CIP funds through an interlocal agreement and adoption of the 2021-2022 CIP that includes updated project cost estimates. There is adequate funding for ...